Wood Floors Over Concrete in Key Biscayne Condominiums: Moisture, Sound Ratings and Glue-Down Specs
How to specify wood flooring over concrete in a Key Biscayne condominium: slab moisture testing, association sound ratings, glue-down assembly and floor height.
Huggins Wood Floor Specialist/

Key takeaways
- Use engineered wood, glued to the slab across its full surface; solid wood is not suited to concrete in South Florida.
- Get the association's flooring rules first. They set the sound rating, the approval process and often the working hours.
- Test the slab for moisture to ASTM F2170 and check flatness to 3/16 inch over 10 feet before ordering.
- In a post-tensioned building, nothing is drilled into the slab without the building engineer's approval.
- Add up the full thickness of underlayment, adhesive and plank, and check it against every door and threshold.
Wood flooring can be installed in almost any Key Biscayne condominium, provided four things are settled before material is ordered: what the association’s rules require, how much moisture is in the slab, how flat the slab is, and how thick the finished floor will be. This article takes them in the order they come up on a project.
Why concrete changes the specification
In most of the country a wood floor is nailed to plywood. On Key Biscayne there is rarely any plywood to nail to. Towers are concrete from the ground up, and houses are concrete slabs at grade or elevated concrete decks. The floor has to be bonded to the slab with adhesive.
That rules out most solid wood, and it makes three properties of the concrete matter: its moisture, its flatness, and how much impact sound it passes to the residence below.
1. Start with the association
Before choosing a floor, ask the association or the building manager for the flooring section of its rules. It normally covers:
- The sound rating required, and the evidence the board wants to see.
- The approval process. Many associations want a written submittal showing the flooring, the underlayment and its test report, and some inspect the underlayment before the wood goes over it.
- Contractor requirements, such as certificates of insurance.
- Working hours, noise windows and service-elevator bookings, which decide how long demolition will take.
- Deposits and protection for corridors and elevators.
A floor designed before this document has been read is often redesigned after it.
2. Sound ratings
Hard floors pass footfall noise to the unit below. Two numbers describe how well a floor and ceiling assembly resists it.
| Rating | What it measures | Typical requirement |
|---|---|---|
| IIC (Impact Insulation Class) | Footsteps and dropped objects | Code minimum 50; many associations ask for more |
| STC (Sound Transmission Class) | Airborne sound such as voices and music | Code minimum 50 |
A few points are easy to miss.
Ratings belong to an assembly, not a product. An underlayment’s published IIC was measured on a particular slab thickness, often with a suspended ceiling below. Compare the tested assembly with your building. A result achieved on an 8 inch slab with a ceiling says little about a 6 inch slab without one.
Delta IIC is the fairer comparison. It reports how much the underlayment alone improves on bare concrete, which makes one product comparable with another.
The floor must not touch the walls. A rigid connection at the perimeter carries sound around the underlayment. An isolation strip at the edge, and baseboard that sits just clear of the floor, keep the assembly working as tested.
3. Slab moisture
Concrete holds water long after it looks dry, and wood glued to a damp slab will cup or come loose.
The test. In-situ relative humidity testing to ASTM F2170 places probes in holes drilled into the slab and reads the moisture inside it. The pass mark comes from the adhesive and flooring manufacturers and is commonly between 75 and 85 percent, with some adhesive systems rated higher.
Post-tensioned slabs. Many towers are built with steel tendons under tension inside the slab. Nothing should be drilled or cut until the tendons have been located and the building engineer has approved it. Where drilling is not allowed, a surface test such as ASTM F1869 can be used, with the manufacturer’s agreement.
Ground-floor slabs and houses. A slab poured on the ground draws moisture from the soil unless there is an intact vapor retarder beneath it. Older houses on the key often have none. In that case the specification includes a moisture barrier on top of the slab, usually a two-part epoxy or the adhesive manufacturer’s own barrier system.
After a leak. Slabs that have been wetted by a plumbing failure, a condensate line or a storm need to be tested again, however dry they look.
4. Flatness and preparation
Glue-down plank needs a slab that is flat to within 3/16 inch over 10 feet, or 1/8 inch over 6 feet. Few slabs meet this once the old floor is up.
- Remove the existing floor. Tile and stone come up with their setting bed. This is the noisiest stage and the one the association’s working hours affect most.
- Clean the slab. Old adhesive, thinset and sealers are ground off so that new products bond to concrete, not to residue.
- Level. Low areas are filled with a cement-based levelling compound that the adhesive manufacturer approves.
- Test. Moisture is tested after preparation, when the slab is in the condition the floor will be laid on.
5. The assembly
A typical condominium floor is built up in this order, from the slab:
| Layer | Purpose |
|---|---|
| Moisture barrier, where required | Stops slab moisture reaching the wood |
| Acoustic underlayment, glued down | Provides the impact sound rating |
| Wood flooring adhesive, full spread | Bonds the plank; some adhesives also add sound and moisture control |
| Engineered plank or parquet block | Sawn oak or walnut face on a cross-laminated core |
Specify products from one adhesive manufacturer where possible, so that a single warranty covers the barrier, the underlayment bond and the wood bond.
The plank. Look for a sawn wear layer of 4 mm or more, a core the manufacturer approves for glue-down over concrete, and an overall thickness of 5/8 to 3/4 inch. Herringbone and chevron follow the same rule and are milled as engineered blocks.
6. Height
The new floor is usually thicker or thinner than what it replaces, and a condominium has many fixed points. Add up the underlayment, the adhesive and the plank, then check:
- The front door, which is often fire-rated and cannot simply be trimmed.
- Sliding-door tracks at balconies and terraces.
- Kitchen appliances that sit under a countertop, especially the dishwasher.
- Bathrooms and other rooms that keep their stone or tile.
- Floor outlets and built-in cabinetry.
A difference of a quarter inch at a threshold can be handled with a shaped transition. A difference of an inch needs a decision before the floor is ordered.
7. Delivery and conditions
Wood should arrive only when the residence is ready for it.
- Air conditioning has been running normally for at least five days.
- Indoor conditions are 60 to 80°F and 30 to 50 percent relative humidity.
- Wet work such as levelling, plaster and paint is finished and dry.
- The flooring’s moisture content is checked on arrival and recorded, along with the slab test results.
Engineered flooring delivered into a conditioned unit needs little time to settle. Flooring delivered into a unit with the air conditioning off needs a different plan, not a longer wait.
Summary specification
| Item | Requirement |
|---|---|
| Association | Flooring rules obtained; submittal approved in writing |
| Sound | IIC to the association’s figure; test report matches the building’s slab |
| Slab moisture | ASTM F2170, within adhesive and flooring limits; tendons located first |
| Flatness | 3/16 in over 10 ft, or 1/8 in over 6 ft |
| Flooring | Engineered, sawn wear layer 4 mm or more, approved for glue-down |
| Installation | Full-spread adhesive; perimeter isolated from walls |
| Site conditions | 60 to 80°F, 30 to 50% relative humidity, air conditioning running |
Once the floor is down, the next question is how to keep it flat through a South Florida summer. That is covered in our guide to humidity, sun and storm season in Key Biscayne homes. To review a specific building and floor together, book a consultation.
The figures here are general industry and building-code guidance. The written requirements of the flooring, adhesive and underlayment manufacturers, and the rules of the condominium association, always govern a specific project.
Questions
Quick answers
What sound rating do I need for wood floors in a Florida condominium?
- The Florida Building Code requires floors between dwelling units to reach an Impact Insulation Class of at least 50, or 45 when tested in the finished building. Many condominium associations set a higher number in their own rules, and the association's figure is the one your floor has to meet.
Can solid hardwood be installed in a Key Biscayne condo?
- It is not recommended. Solid wood needs a plywood subfloor to be nailed to, which adds height and weight, and it moves far more than engineered wood in South Florida humidity. Engineered plank with a thick sawn face looks the same, can be refinished, and is made to be glued to concrete.
Do I need association approval to install wood floors in a condominium?
- In most buildings, yes. Associations usually ask for a written submittal showing the flooring, the acoustic underlayment and its sound test report, and approve it before work begins. Some also inspect the underlayment before the wood is laid over it. Starting without approval can mean taking the floor up again.